On Saturday at around 9:30 a.m., Aug. 8, 52,373 of Con Edison’s 360,045 customers are without power (14.6 percent), and 4,629 of NYSEG’s 33,278 customers in Northern Westchester (13.9 percent) were reporting outages.
Con Ed has estimated that power will be restored no later than 11 p.m. on Monday, Aug. 10. NYSEG has not provided an estimated time of restoration.
The most outages are in Yonkers, New Rochelle, Mamaroneck Village, Mount Vernon, Bedford, New Castle, Somers, Mamaroneck Town, Cortlandt, Mount Pleasant, Lewisboro, White Plains, Yorktown, Peekskill, Rye and Scarsdale..
Con Edison said it has more than 1,650 field workers on the job and is getting help from 819 mutual aid and contractor workers from as far away as Texas, Florida, Iowa, and Wisconsin.
An additional 311 workers were scheduled over the weekend.