NORTH HALEDON, N.J. -- Into the fall, PSE&G will continue working to replace approximately 19 miles of aging cast-iron gas pipes in North Haledon.

PSE&G will continue to update gas pipes and mains on many of North Haledon's roads, as highlighted here.

PSE&G will continue to update gas pipes and mains on many of North Haledon's roads, as highlighted here.

Photo Credit: Google Maps

The old pipes and mains will be replaced with new, durable plastic or coated steel piping.

Work will done Monday through Saturday, between 7 a.m. and 6 p.m., weather permitting. The work began this months, and while the main work should be done by August, it will be into fall before all the repaving is finished.

You can view more project details here. Call PSE&G's Oakland Gas district office at 201-337-2519 with any questions.