The goal is to mill on Route 136 to roughly a quarter-mile south of Route 25, just short of four miles in total.
The DOT plans to start paving that area on Monday, July 5, aiming to finish on Wednesday, July 15.
All DOT work is part of a larger project to resurface Route 59 in Easton and Monroe.
Be aware that inclement weather will likely change the schedule, and any questions can be forwarded to Rich Porter, DOT Transportation Maintenance Planner , by calling (203)-389-3035.