Work resumed this week on the Route 123 bridge. The anticipated completion date is now November not August, said Sen. Bob Duff (D-25) who called a press conference yesterday morning to share the latest information about the ongoing project to replace the 70-year-old bridge that crosses the Norwalk River.
The project came to a halt last October following a disagreement between the Department of Transportation and Connecticut Light & Power over five circuit lines that are fastened to the bridge. The two parties did not agree on who would assume liability for moving the cables, one of which supplies power to Norwalk Hospital. Work was further delayed when damage from the March storms diverted CL&P crews, said Duff.
This has been an example of how not to run a public works project, said Duff. He held bi-weekly discussions with CL&P to monitor progress and he commended their responsiveness.
Old steel girders visible to passersby should come down in the next two weeks, said the project manager for the contractor, Mohawk Northeast. He declined to give his name but said materials for the new bridge sit in Pennsylvania and are ready to be shipped.
This is a very dangerous intersection, said Duff. We will be working with the DOT and looking for ways to maximize safety.