I-84 Bridge Work Over Route 9W Starts

Work is underway on an extensive, multi-million dollar project to rehabilitate the Interstate 84 bridge over Route 9W in Newburgh.

Looking toward the Newburgh-Beacon Bridge from Long Dock Park in Beacon.

Looking toward the Newburgh-Beacon Bridge from Long Dock Park in Beacon.

Photo Credit: Skip Pearlman

The $14.7 million project will raise the height of the overpass from 14 to 16 feet at the interchange. The funding was awarded by the New York State Bridge Authority in late February.

During construction - which is expected to last for nearly two years - will be done two lanes at a time, from south to north, and is expected to be completed in 2020. While work is ongoing, westbound traffic on I-84 will be limited to two lanes from 8 a.m. to 3 p.m. on weekdays.

Keep following Daily Voice for updates on the project as it begins on Monday morning.