SHARE

Hoboken PATH Station Closing In February For Repairs: Port Authoit

As part of a repair project, the Port Authority announced the PATH Hoboken station will be closed from Thursday, Jan. 30 to Tuesday, Feb. 25.

Hoboken's PATH station will be closed for mot of February.

Hoboken's PATH station will be closed for mot of February.

Photo Credit: PATH Twitter

The move comes as part of the agency's two-year $430 million PATH Forward program.

During the closure, the Port Authority will carry out critical safety repairs and improvements across several elements of the 116-year-old system. The Port Authority said the full station closure enables it to complete track and station work on an expedited basis that would otherwise necessitate severe schedule reductions and service suspensions repetitively over a prolonged period. 

Track work will include replacing in-station track, replacing the track switching network outside the station, and repairing 4,500 linear feet of track leading to the station. Station work will include refurbishing the concrete platform surface and replacing four stairways between the station’s mezzanine and platform levels.

Alternative services being offered during the closure include expanded ferry service, frequent shuttle buses to other PATH stations, and supplemental PATH, light rail, and NJ TRANSIT bus service between Hoboken and Manhattan.

Hoboken station will close at  11:59 pm. on Thursday, Jan. 30 and  reopen at 5 a.m. on Tuesday, Feb. 25. 

Repairs include:

Replacement of Hoboken Interlocking and tracks: PATH will replace in-station tracks and the Hoboken Interlocking, the intricate system of tracks and switches that allows all service from two tunnels to access three tracks at the Hoboken station. Without the continuous 25-day outage, this work by itself would require four complete weekend shutdowns due to the scale and location of the interlocking, and an additional 50 consecutive days of significantly reduced service levels in and out of Hoboken due to the reduction in station track capacity required to maintain safe operations during the construction, the Port Authority said.

Track repair and maintenance work: PATH will repair 4,500 linear feet of track in the two tunnels leading into the station. The continuous 25-day outage prevents a full year of weekend service reductions that would otherwise be required to complete the work.

Restoration of passenger infrastructure: PATH will replace the concrete walking surfaces in public areas throughout the station and replace four staircases between the station’s mezzanine and platform levels. Performing the most disruptive work during the outage will reduce a 28-weekend timeline of disruption to customers at Hoboken, th Port Authority said.

to follow Daily Voice Nutley and receive free news updates.

SCROLL TO NEXT ARTICLE