Little Ferry Circle Project Right On Schedule

LITTLE FERRY, N.J. — The reconstruction project at what was once known as the Little Ferry Circle at Route 46 and Bergen Turnpike will be completed by the end of the year, as scheduled, officials announced Monday.

Little Ferry Mayor Mauro Raguseo and Councilman Ron Anzalone at the briefing.

Little Ferry Mayor Mauro Raguseo and Councilman Ron Anzalone at the briefing.

Photo Credit: COURTESY: Little Ferry Mayor Mauro Raguseo
Water drainage system to the river.

Water drainage system to the river.

Photo Credit: Mauro Raguseo
Debris removal system at the pump station.

Debris removal system at the pump station.

Photo Credit: Mauro Raguseo
New landscaping getting planted.

New landscaping getting planted.

Photo Credit: Mauro Raguseo
Electrical paneling inside the pump station building.

Electrical paneling inside the pump station building.

Photo Credit: Mauro Raguseo

Final paving should begin within the next few weeks and upper bridge work will continue through December, causing lane shifts for the removal of bridge gates, local officials were told during a briefing this morning by the New Jersey Department of Transportation and Conti Construction.

A pump station should be in operation in late November. Landscaping and beautification have already begun.

“A few more weeks of annoying traffic but the results of the project will be worth it,” said Little Ferry Mayor Mauro Raguseo. “Progress in Little Ferry!”