So far, builders have completed the installation of the learning commons carpet and shelving. Additionally, the tiling has been installed in the learning commons, the storage room, and the science lab.
The cabinets on the first floor are being installed as they arrive on site. Installation of the ceiling tiles is getting underway, and contractors are continuing to check for other signs of water leakage and flooding.
Evidence of water damage was discovered in a section of wall in the music room that had previously been considered unaffected. This section of wall has since been replaced and does not impact the completion date.